Lom Pangar Dam Fact Sheet
Terri Hathaway (International Rivers) and Halleson Durrell (GVC)
The
government of Cameroon is currently considering building the Lom Pangar
Dam, a project that would displace rural villagers, flood protected
forests, and increase the vulnerability of Cameroon’s economy to
climate change. Increased hydropower generation downstream of Lom
Pangar would mostly go to a large, foreign–owned aluminum smelter,
which is expected to continue receiving below–cost electricity rates
subsidized by residential ratepayers. The dam has been discussed for
over a decade, but with a growing national energy crisis, the
Cameroonian government has recently intensified efforts to obtain
financing for the project.
1. The Wrong Solution for a Warming World
Lom Pangar would be the fourth dam1
built to help regulate the Sanaga River for the benefit of the
country’s two primary hydropower dams, Song Loulou (384 MW) and Edea
(264 MW). These run–of–river hydropower dams have experienced
significant reductions in power generation due to dry seasons
exacerbated by drought. The Government of Cameroon hopes the Lom Pangar
Dam will increase these dams’ ability to generate power during dry
periods by an estimated 105 MW to 216 MW.2
This increased electricity would assist the southern Cameroon grid’s
capacity, where the Alucam aluminum smelter is seeking to double its
production.3
The dam, proposed for one of the Sanaga’s most important tributaries,
could significantly alter the river ecosystem, as well as submerge one
of Africa’s most biodiverse hardwood forests (see section 6). The
cumulative ecological impacts of adding yet another dam to this river
system are unknown, but could be great.
| Fast Facts |
|
Location: Lom River (Eastern Cameroon)
4 km downstream from the confluence of the Lom River and Pangar River, and 13 km upstream from the Sanaga River.
Purpose:
Regulation of the Sanaga River to increase power generation of 2
downstream hydropower plants, Song Loulou and Edea, during the dry
season; hydropower generation at Lom Pangar for the Eastern grid.
|
Dam height: 50 meters
Reservoir Size: 610 km2
Estimated Construction Cost:
US $115 million4
Installed Capacity: 51 MW
Construction Timeline: 2005 – 2008
|
|
KEY CONCERNS:
- Cameroon
is already 95% dependent on hydro for its electricity; reduced power
dependability because of drought is already an issue, and could worsen
with climate change.
- Despite extremely low levels of
electrification for Cameroonian households (less than 5%), the
project’s primary beneficiary will be the Alucam aluminum smelter,
which already consumes about half the nation’s electricity at rates
subsidized by residential users. Small business and residential
customers will remain at risk of blackouts and power shortages.
- The
reservoir will displace several villages, flood the protected Deng Deng
Forest, and negate protections designed under the World Bank sponsored
Chad–Cameroon Pipeline.
|
|
Technical Partners:
Environmental Impact Assessment (EIA):
Conducted by French companies: ISL, Sogreah, and Oreade; funded by the Government of Cameroon and French Development Agency5
|
Private Electric Utility: AES–Sonel
Independent Expert Panel: to review the EIA; facilitated by IUCN, funded by the Government of Cameroon and GTZ6 (a German aid agency)
|
|
The World Bank’s 2003 Country Assistance Strategy (CAS) for Cameroon states:
The
Lom Pangar dam has raised some concerns for the World Bank Group
because of potential negative social and environmental impacts related
to long–term and cumulative changes in the Sanaga river system flow
regime. The flooding of a large dam catchment area would affect a
portion of the Deng–Deng forest, a biodiversity hotspot explicitly
protected under current arrangements in the context of the
Chad–Cameroon Pipeline project. A costly adjustment was made to the
pipeline route to avoid going through the central Deng Deng forest
areas and avoid other dense forest areas.7
Hydropower already accounts for 95% of Cameroon’s electricity supply,virtually all of which is generated on the Sanaga River.8
In addition to Lom Pangar, the government has stated its intentions to
build another dam on the Sanaga River, the Nachtigal Dam (266MW),
further increasing the nation’s dependence on this river basin. This
heavy dependence on hydro (and one river system) puts Cameroon at great
risk for economic disruptions caused by droughts. In 2002, low rainfall
resulted in blackouts during the dry season that drove up unemployment
and business costs. Electricity generation has been further hampered by
reservoir sedimentation and poor maintenance of the dams. But the
government appears set on further exploiting hydropower rather than
diversifying its energy resources (see section 9). Cameroon’s President
has reportedly signed a financial agreement with the China
International Water and Electrical Corporation (CWE) to assist in
building three hydropower dams in Cameroon.9
It
is unclear how effective the Lom Pangar Dam would be in regulating the
river for better power generation in the face of ongoing droughts and
unpredictable climate change. The World Bank has expressed concerns to
the government of Cameroon about its energy mix, stating:
...the
current high rate of dependence of electrical power generation in the
country on hydropower dams ... makes for high vulnerability to seasonal
and longer–term cyclical changes in rainfall and hydrology.10
The 2003 CAS also states:
In
response to Government concerns about reliable and affordable
electricity, a more comprehensive examination to explore various
scenarios to address short, medium, and long term needs, explicitly
incorporating social and environmental concerns, is being undertaken.11
2. Project Origins
In
July 2001, the US–based AES Corporation and the government of
Cameroonsigned a concession agreement for the World Bank/IFC–advised
privatization of Sonel, Cameroon’s state–owned electric utility. As
part of the 20–yearcontract, AES agreed to develop the Lom Pangar Dam
within seven years if it were found to be the least cost option.12
Since privatization, electricity rates for residential consumers have
increased by more than 10%. Price hikes led to street protests during
massive blackouts in 2002. The World Bank has since expressed concerns
about the privatization of Cameroon’s electricity sector. A February
2004 Bank report states:
Only
one investor presented a bid ... and was designated as a successful
bidder. However, post–privatization performance has been disappointing.
The privatized electricity company has not been able to deliver
services in the hoped–for combination of quantity and quality owing to
several factors, including a severe drought during 2001 and 2002. The
significant load–shedding that occurred has caused economic disruption
and public outrage.13
3. Current Status
Multiple
feasibility studies for Lom Pangar were conducted in the 1990s, and,
according to IUCN, an updated analysis was completed by the French
Development Agency (AFD) in 2000.14
A new environmental impact assessment (EIA), led by the French company
ISL, is expected to be completed in mid–2005. A three–member
Independent Panel of Experts, facilitated by IUCN, has been established
to review the EIA for compliance with international standards on the
project’s social and environmental impacts. If the project is approved
and financing obtained on the basis of these assessments, construction
could begin soon and be completed as early as 2008.
4. Benefiting Big Aluminum
Aluminum
smelting is an energy–intensive industry that often seeks below–cost
energy contracts. AES–Sonel’s largest customer is the Alucam aluminum
smelter, owned by the Canadian company Alcan. Alucam currently consumes
nearly half of the energy sold by AES–Sonel. Interested in doubling its
aluminum production, Alucam is seeking up to 200 megawatts of
additional electricity in order to expand its operation, at rates far
lower than commercial and residential rates.15
Before the privatization of Sonel, Alucam was paying below cost for its
electricity, and just one–tenth the rate charged to residential (“low
voltage”) consumers.16
Local activists have spoken of the "disheartening equity concerns" over
the government’s favoritism toward Alucam. About 95% of Cameroonians do
not have access to electricity.17 If Alucam expands operations as planned, small businesses and residential users would see little benefit from Lom Pangar.
The World Bank has concerns about Alucam’s energy use, and talked to Cameroon authorities about:
links
between the imperative of expanding low–cost power generation capacity
and the substantial requirements for aluminum smelting (which currently
benefits from below–cost power), and is encouraging and offering to
assist with an in–depth assessment of the optimality of aluminum
smelting operations (especially an intended expansion of such
operations) as an integral part of assessing long–term options for the
expansion of power generation capacity.18
5. Dam–Affected People
The
large reservoir necessary for this project will dislocate a number of
villages, requiring resettlement in the outer regions of Pangar. In
January 2004, traditional chiefs of local villages met with state
authorities and were told their communities would be displaced and
resettled.19
There is great concern, however, about the implementation of these
measures. Complaints from locals are being compiled for review. Many of
these villagers, already impacted by the Chad–Cameroon Pipeline, are
wary of Lom Pangar. In 2004, locals told the Independent Expert Panel
that they needed more information about the project, especially about
its benefits and environmental risks.20
The
Expert Panel’s initial report (April 2004) details the history of dam
projects in Cameroon, specifically noting the lack of energy benefits
and job opportunities materializing for affected communities, while
increased health risks have strained over–burdened local health care
systems. Since other dam projects in Cameroon have brought large
numbers of migrants and commercial fishermen to their reservoirs, local
populations are also concerned about the influx of new people to the
Lom Pangar region, leading to increased demands on local resources such
as hunting and fishing grounds.
6. Drowning the Deng Deng Forest
The
Lom Pangar reservoir would submerge areas protected as mitigation for
environmental impacts of the World Bank–sponsored Chad–Cameroon
Pipeline, including parts of the Deng Deng Forest. The Deng Deng Forest
(part of the greater Guinea Forest) not only has one of the highest
levels of biodiversity in Africa, it is also one of the last remaining
hardwood forests on the continent. For these reasons, great attention
was given to protecting the forest from direct and indirect impacts of
the pipeline. Yet the ecological value of the Deng Deng Forest has not
been included in the cost–benefit analyses for Lom Pangar.
Cameroon
has already experienced massive deforestation due to logging for export
(primarily to Europe and Asia). Almost half of Cameroon’s historic
forest area has been cleared for agriculture and settlements.21
The government of Cameroon is reportedly very interested in logging the
high–priced tropical hardwoods found in the Deng Deng. Anonymous
sources report that concession agreements to log the forest have
already been signed, and logging roads into the area are rumored to
already be built. Additional access roads that would be built for dam
construction could lead to increases in illegal logging and corruption
in the region, already a widespread problem in Cameroon.
Due
to controversy surrounding the pipeline, the World Bank assembled an
International Advisory Group (IAG) to oversee the implementation of the
project. IAG reports have consistently noted the risks of the Lom
Pangar Dam. Following are some relevant excerpts:
There is an even greater potential threat to the [Deng Deng]
site from the possible construction of a hydroelectric dam across the
Lom–Pangar. This would flood a part of the protected forest (as well as
part of the pipeline).22 (June 2003)
If
this dam is constructed, a large portion of the Deng–Deng forest will
be submersed, as well as part of the pipeline, which was not
constructed with this eventuality in mind.23 (January 2004)
[The IAG finds policies for environmental protection have not been implemented.] These
legal and technical voids increase the risk of impact on the
environment and hence on the population, not only for the pipeline
Project but for other major projects to come, such as the Lom–Pangar
dam...24 (July 2004)
Destroying
these protected areas will result in a serious violation of trust for
all those involved in ensuring that environmental safeguards were
respected for the Chad–Cameroon Pipeline. The World Bank’s reputation
will suffer a serious blow should the project go forward unimpeded by
previous World Bank agreements to protect the Deng Deng.
7. Uprooting the Chad–Cameroon Pipeline
The
construction of Lom Pangar, as designed, would not only result in the
destruction of the forest that the pipeline project team sought to
preserve, but the dam’s reservoir would submerge the land under which
20 km of the pipeline crosses. Because it was not built to withstand
the extra pressure of the reservoir, the pipeline would have to undergo
a costly excavation and either be rerouted or reinforced, resulting in
a stop in oil flow for a period of time, with associated costs, as well
as unknown environmental and social risks, such as additional damage to
land and spills.
After formal complaints about
the World Bank’s Pipeline project were received, the independent
Inspection Panel noted in its investigation report that the Lom Pangar
Dam would:
...pose a problem
for the integrity of the Pipeline Project since it would have to be
re–excavated and concrete weighting provisions added. It would also
possibly threaten the newly established Mbam Djerem protected area as
water access would now be provided.25
Project
sponsors have already spent a good deal of money ($18 million by some
accounts) re–routing the pipeline to avoid the Deng–Deng Forest. It is
currently unknown how much money it will cost to reroute the pipeline
or reinforce it to withstand a reservoir, but clearly these costs would
be substantial, and could conceivably be put to better use, such as
supporting poverty reduction projects in local villages or improving
protections for Cameroon’s remaining biodiversity hotspots. Project
insiders believe that re–routing the pipeline for the dam could lead to
a confrontation between project sponsors and the Cameroon government
over who should shoulder the added costs, as well as over the legality
of flooding the protected forest areas.
8. The Way Forward
After
a global review of large dam projects, the World Commission on Dams
(WCD) released its final report in 2000, which set forth
recommendations for a transparent, multi–stakeholder process to
objectively assess a nation’s water and energy needs and choose
appropriate options.26
The WCD’s recommendations, if followed, would help ensure that a
particular large dam project has been found to be the most effective
solution while guaranteeing that affected communities share project
benefits without disproportionately bearing the project’s risks. To
follow WCD recommendations, a project must start with a needs
assessment rather than starting with a proposed solution to an
undefined problem. A needs assessment is followed by an options
assessment that engages all stakeholders and utilizes a transparent
decision–making process.
The Cameroon government
is attempting to show compliance with WCD recommendations by utilizing
an Independent Expert Panel to review the project’s EIA. The Expert
Panel is charged with ensuring that Lom Pangar complies with
international standards for social and environmental impact mitigation,
including the WCD and World Bank safeguard policies,27
and will assist with public consultations and mediation should
environmental disputes arise. The panel was originally contracted for
one year (until December 2004, though work is continuing) and is being
facilitated by the IUCN. While an admirable effort, the Expert Panel
will only assess the environmental review, not the project in its
entirety. The Panel’s mandate leaves out vital parts of the WCD
recommendations, and will likely result in a weak approach to assessing
the project, and broader national energy planning processes, without
significant comparison against the WCD.
9. Project Alternatives
While
the EIA is expected to include a limited analysis of project
alternatives (though not necessarily ones that have been fully
evaluated to the extent that Lom Pangar has been), comprehensive needs
or options assessments for Cameroon’s energy sector have not been made
public. While the need for more reliable electricity is clear, the
public has not been involved in the energy planning process thus far.
The construction of Lom Pangar Dam will happen without the benefit of a
comprehensive and participatory options assessment.
Cameroon
has great potential for saving energy through demand–side management
and efficiency measures. Over 30% of the electricity generated in
Cameroon is lost during transmission.28
Improving the efficiency of transmission lines could go a long way to
lowering Cameroon’s need for additional power. AES–Sonel also notes
that most power stations have been neglected and need sizable repairs.29
It is not clear that demand–side options are being fully considered
prior to new supply projects such as Lom Pangar or thermal power plants.
Cameroon also has a large reserve of natural gas. The World Bank states:
Cameroon’s
natural gas potential has not been fully explored or exploited. While
much of the natural gas was flared in association with oil production,
nonassociated gas was left untapped. Domestic use of natural gas would
assist the country’s development in the following ways:
-
The
introduction of gas for power generation, which should be considered in
the longer term as an alternative to costly hydro schemes;
-
The
use of gas as fuel in the conventional industry, to save oil for
exports while improving the performance of Cameroonese industrial
sector.30
AES–Sonel
is currently undertaking development of natural gas and oil power
stations to help diversify Cameroon’s energy resources, but progress
has been slow. AES–Sonel is also currently contracted with the
Institute of Geological and Mining Research for renewable energy
research, but the contract is only for one year and renewable energy
development and decentralized, rural electrification do not appear to
be priorities.31
10. Conclusions
Insiders
have said that the Cameroon Government has every intention of building
the Lom Pangar Dam and that completing the EIA and using the Expert
Panel are simply necessary steps to appease international donors.
However, the dam is not being assessed against other energy
alternatives in a comprehensive needs and options assessment. Nor is
the process being made transparent or open for public participation.
Transparency has been named a goal by the government, but needs to be
demonstrated by real engagement of affected communities in the project
process, and release of the AES–Sonel concession agreement and Lom
Pangar studies.
The World Bank, too, must take a
public stand on this project and its impacts on protected forests
offset for the Chad–Cameroon Pipeline. As one former project staffer
said, “This project poses huge risks for the Bank’s reputation. We need
to follow through on our promises. This is a moral issue.”
© May 2005
International Rivers
Welcome to International Rivers' website
-
Mapé
Dam is located on the Mapé River; Mbakaou Dam is located on Djerem
River; and Bamendjin Dam is located on the Noum River. Independent
Expert Panel, Rapport de Mission, 17 April 2004..
-
Quotes include 105 MW (UNDP / WB ESMAP, Africa Gas Initiative Cameroon Volume III, February 2001, p. 31); 170 MW (OECD, African Economic Outlook – Cameroon, 2004, p.103); and 216 MW (‘Cameroon Country Profile’, International Water Power & Dam Construction).
-
UK Trade & Investment, Electricity Market in Cameroon, www.trade.uktradeinvest.gov.uk.
-
UNDP / WB ESMAP, Africa Gas Initiative Cameroon Volume III, February 2001, p. 31.
-
OECD, African Economic Outlook – Cameroon, 2004, p.103.
-
F. Neumann–Silkow, E. Hellstern, H. Brühl, Implementation of the WCD recommendations within German Development Cooperation, Deutsche Gesellschaft für Technische Zusammenarbeit (GTZ) GmbH, June 2004, p. 18.
-
Cameroon Country Office, Country Assistance Strategy, World Bank, 14 August 2003, p. 20..
-
Ibid.
-
‘Chinese Dams?’, Africa Energy Intelligence No.356, 28 October 2003; ‘China to fund hydro–electric dam projects in Cameroon’, Agence France–Presse, 8 October 2003.
-
Management Report and Recommendation in Response to the Inspection Panel Investigation Report, World Bank, 10 June 2003, p. 13.
-
Cameroon Country Office, Country Assistance Strategy, World Bank, 14 August 2003, p. 20.
-
Anonymous, 29 September 2004; C. Akong, ‘Power Privatization in Cameroon, the Chad Oil Pipeline and Skewed Development’, Pambazuka News, 19 February 2004.
-
Third
Structural Adjustment Credit (Credit No. 3102~CM) Release of the Second
Privatization Support Floating Tranche – Waiver of Two Conditions and
Release of the Transport Support Floating Tranche – Partial Waiver of
One Condition, 25 February 2004, p. 4.
-
www.iucn.org
-
WB Management Report and Recommendation in Response to the Inspection Panel Investigation Report, World Bank, 10 June 2003, p. 13.
-
C. Akong, ‘Power Privatization in Cameroon, the Chad Oil Pipeline and Skewed Development’, Pambazuka News, 19 February 2004.
-
www.camnet.cm
-
WB Management Report and Recommendation in Response to the Inspection Panel Investigation Report, World Bank, 10 June 2003, p. 13.
-
A. Chedjou, ‘Barrage de Lom–Pangar: Les villageois inquiets’, Journal Bubinga, 7 June 2004.
-
Independent Expert Panel, Rapport de Mission, 17 April 2004.
-
www.globalforestwatch.org
-
IAG, Report of Visit to Chad and Cameroon April 21 to May 10, 2003, June 2003, p. 32.
-
IAG, Report of Visit to Cameroon December 1 to 5, 2003, 28 January 2004, p. 5.
-
IAG, Report of Visit to Chad and Cameroon May 17 to June 5, 2004, 9 July 2004, p. 26.
-
Inspection
Panel, Cameroon: Petroleum Development Pipeline Project and Petroleum
Environmental Capacity Enhancement, 12 May 2003, p. 37.
-
WCD, Dams and Development: A New Framework for Decision–Making, 2000.
-
Independent Expert Panel, Rapport de Mission, www.iucn.org, 17 April 2004.
-
OECD, African Economic Outlook – Cameroon, 2004, p.102.
-
S. Tetchiada, ‘Flicking the Switch on Growth’, IPS News Service, 4 August 2004.
-
www.worldbank.org
-
J. Pefok, ‘AES–SONEL Signs Convention to Improve Generating Facilities’, The Post, 16 February 2004.